2nd Riverfront Tower on Schedule

May 29, 2010

Construction of Riverfront Place’s second condo tower is on schedule for its fall 2011 opening.

Workers from Boyd Jones Construction of Omaha are completing the seventh of the tower’s 15 floors and are pouring a new floor every two weeks, said Loretta Carroll, a spokeswoman for the project. Installation of glass should start within two weeks.

More than half of the condos are sold.Riverfront Place Tower II from completed Tower I May 28, 2010